Campana Refinery

Client

Axion Energy (Argentina)

Plant

Atmospheric Distillation Unit (ATU) & Crude Vacuum Unit (CVU)

Project Type

Modernization (Revamp)

Scope

Conceptual and Extended Basic Engineering

Investment value

USD 200 M

As part of its ambitious 2012 expansion plan, Axion Energy has modernized its Campana refinery, incorporating new key units such as the Atmospheric Distillation Unit (ATU) and the Vacuum Distillation Unit (CVU). These installations allow the heaviest crudes to be processed as efficiently as possible, enabling a more thorough oil conversion. This has allowed for the maximization of clean combustible production under Euro regulation and has proven Campana to be one of the most advanced refineries in the region.

Hytech conducted both the Conceptual and Basic Extended Engineering for this project, developing modifications to the traditional configuration of an atmospheric distillation column and vacuum, and incorporating an additional intermediate column operated under vacuum to eliminate bottlenecks. This new column improves the fractionation of the most valuable gasoil and reduces the recovery charge in the second column.

Hytech carried out an integral analysis of each unit and the general auxiliary services and specifications of the complex, identifying bottlenecks through the verification of each of the process equipment (Columns, Preheaters, Air Condensers, Pumps, etc.).

editada2 (1).jpg

Integrated engineering solutions were developed, including a new Preflash Vacuum Column, a new multi-client oven for crude and reduced crude, and the modification of the recuperation of distilled products.

60% GREATER CAPACITY

Increase in the nominal capacity of crude processing, from 82 kbpd to 130 kbpd.

28% GREATER RETURN

Increase in yield of distilled gasoil product.

ARGENTINA (Headquarters)

Buenos Aires, CABA 

Suipacha 1111

5th floor

ZIP: C1008AAW

+54 11-4314-0134

Neuquén Capital

Central de Oficinas

Dr. Ramón 87

Of.: 205 ZIP: 8300

Santa Fe Capital

Free Work - Espacio Chacabuco

Chacabuco 1880

ZIP: 3000

USA

Houston

North Loop West 1415

C.P.: Q8305 Ste.: 300-13

+1-832-289-3551

1e0901_6539eb7354564d61ad23d28ae723edd0.png
  • Instagram
  • LinkedIn
bottom of page