Scope
Conceptual Engineering, Basic Engineering, Extended Basic Engineering, Detailed Engineering, Local Procurement, Manufacturing and Construction Assistance, Pre-commissioning, Commissioning, and Start-up
The Sierras Blancas Central Processing Facility (CPF) was a milestone for Shell’s production in Argentina, tripling the installed processing capacity. This advancement marked Shell’s move toward large-scale development in Vaca Muerta.
Hytech worked with a clear objective to minimize field activity during the unprecedented challenges of the global pandemic. To achieve this, a modular strategy was designed that included prefabricated equipment, pipe racks, and concrete sleeper-type foundations.